News & StoriesCareers

July 24

2020

Pastor Brown swings the first hammer to kick off demolition and the construction on the Women's and Children's Shelter

August 25

2020

The Fence is put up around the construction site and one of the lanes on Burdick St is closed.

August 26

2020

Excavating equipment arrives to the construction site

September 16

2020

The first bricks begin to fall as the first part of the building comes down.

September 18

2020

The demolition crew tear down the first of the three buildings on Burdick St.

September 21

2020

Demolition on the 2nd building begins.

September 22

2020

The construction crew finishes tearing down the second building and moves onto the third and final building

October 9

2020

Demolition is completed on the third and final building. The demolition crew continues to remove debris, clearing the way for the new foundation to be poured